Is it possible to synchronize to RTC project areas ?


Sunanda Kalthireddy (15311) | asked Jun 19 '17, 3:56 a.m.

 Hello Team,


My first question is, is it possible to synchronize two RTC project areas. if i create a wi in RTCPA1 , wi should be reflect to RTCPA2.

is there any way to do this?

2.) what is association in RTC Project area? how it will work ?

Thanks in advance.

One answer



permanent link
Ralph Schoon (63.4k33646) | answered Jun 19 '17, 4:02 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 1) There is no built in capability available. It is certainly doable using a custom synchronizer, with all the issues synchronizer have. Task Top could be an option.

2) I am not sure what you ask.