Story point addition to a parent in another project


Vijay Sivashankar (111317) | asked Mar 30 '17, 2:29 p.m.

 I have one project where we have the offering management stories and another project where we are tracking the development stories. Development stories are parented to offering management stories in the offering management project.

Both projects are on the same RTC instance.

Child story points are getting added up within the development project, but the story points are not getting added to the top parent in the offering management story. Is there any way to get this reflected?
      OM Story
            |_ Dev Story 1 - 1/5 Points Completed
            |_ Dev Story 2 - 2/3 Points Completed

I want the OM Story to indicate 3/8 Points Completed
  


Comments
Kevin Ramer commented Mar 30 '17, 3:37 p.m.

Wouldn't that be 13/15  ?  :-D

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Apr 03 '17, 5:10 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 The RTC complexity calculation for parent/child relationships only works within one project area. It was designed that way and there is no way to change this. You could try approaches like participants as explained in  https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ . This has obviously an impact on performance and is not the same. 


 