Importing MPP file into RTC Plan with Custom Fields
![]()
Salman Shaikh (234●1●19●72)
| asked Mar 26 '17, 10:57 a.m.
retagged Mar 31 '17, 10:31 a.m. by Ken Tessier (841●1●7) I have a MPP Plan file having Attributes (System , Subsystem and Task Type) I have the same attributes in RTC Plan and in task work item. The above fields are marked mandatory as well.
|
2 answers
![]() If I'm not mistaken, the RTC Import wizard requires that you import the XML file. See Importing and exporting plans with Microsoft Project and Importing, exporting, and reimporting project plans in the web client for details.
Ken
|