Time Spent Attribute not showing in the"Add Attribute" in JRS


Eamon Horkan (21216) | asked Jan 18 '17, 5:13 a.m.

 Hi  , 


can anyone explain why I cannot find the Time Spent attribute to add it into a report. Is there any way to me make the attribute available for selection ? 

Best Regards , 

Eamonn 

Accepted answer


permanent link
Lily Wang (4.9k714) | answered Jan 18 '17, 5:55 p.m.

 The Estimate and Time Spent attributes are actually shown as "Planned Work" and "Actual Work" in JRS. The value are shown in seconds.

Ralph Schoon selected this answer as the correct answer

One other answer



permanent link
Eamon Horkan (21216) | answered Jan 26 '17, 10:48 a.m.

 Hi Lily ,  Many thanks , actual work is where its recored , just a shame that it is in seconds ! 


Thanks 

Eamonn 