Hi All,

I want to create new work item after a particular work item gets saved.

I looked at the article https://jazz.net/wiki/bin/view/Main/ProgrammaticWorkItemCreation to create work item but that is using Plain client libraries. Is there any similar reference that shows how to create work items in Operation participants or advisors ?

Thanks
Akshay P.

One answer



permanent link
Arne Bister (2.6k12832) | answered Jun 18 '16, 1:13 p.m.
JAZZ DEVELOPER
Akshay,

please check the example in Ralp Schoons Blog, e.g. https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/

This uses server side code, also points out how to avoid recursion in the participant.
If this is useful to you please mark the answer as accepted.

- Arne

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.