Should I always stop the applications first before turning off IHS?


Krzysztof Kaźmierczyk (7.4k373103) | asked Jan 29 '16, 2:16 p.m.
I am already starting using a distributed topology in CLM solution and I would like to know the restart sequence.

Should I always stop the IBM Collaborative Management (CLM) applications first before turning off IBM HTTP Server (IHS)?

One answer



permanent link
Krzysztof Kaźmierczyk (7.4k373103) | answered Jan 29 '16, 2:17 p.m.
CLM applications need to connect between each other. The communication goes through proxy server. Therefore to avoid connection errors in CLM applications you should stop CLM applications before stoping IHS.