Pnina Lavie (46421) | asked Nov 11 '15, 10:17 a.m.
 We're working in Agile ALM process template and we  get Change Requests of the following types: request to change Requirement/ Plan/ Timeline/ KPI etc... Where is it more appropriate to issue such change-requests? RTC or RDNG (we have CLM 5.2 and it hasn't any Change Request Work Item/Artifact by default)

One answer



permanent link
Daniel Moul (4.9k1318) | answered Nov 11 '15, 11:27 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
I recommend creating a work item type of "change request" and use it for any of those kinds of changes.  Where multiple people need to do work or make changes in multiple tools, you can use multiple change requests (one parent and multiple children).

Comments
Pnina Lavie commented Nov 12 '15, 5:30 a.m.

 Thanks! it answers my question.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.