What is the right place to issue change requests? in RTC or RDNG?

 We're working in Agile ALM process template and we  get Change Requests of the following types: request to change Requirement/ Plan/ Timeline/ KPI etc... Where is it more appropriate to issue such change-requests? RTC or RDNG (we have CLM 5.2 and it hasn't any Change Request Work Item/Artifact by default)

0 votes



One answer

Permanent link
I recommend creating a work item type of "change request" and use it for any of those kinds of changes.  Where multiple people need to do work or make changes in multiple tools, you can use multiple change requests (one parent and multiple children).

1 vote

Comments

 Thanks! it answers my question.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,014

Question asked: Nov 11 '15, 10:17 a.m.

Question was seen: 3,313 times

Last updated: Nov 12 '15, 5:30 a.m.

Confirmation Cancel Confirm