It's all about the answers!

Ask a question

Detemining inactive projects in RTC/RQM


Vishnu Kumar (2621627) | asked Sep 29 '15, 9:54 a.m.
Hello Everyone,

We are in the process of archiving inactive projects at RTC/RQM.

What is the best way to filter out such dormant projects those have not been used for last 6 months ?

Inactive: No element/work item/reports/user have been added to the project.

Regards
Vishnu Kuma

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Sep 29 '15, 10:57 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
edited Sep 29 '15, 11:03 a.m.
For RTC: Consider to look at the team events and run a work item query for the last modification.
For RQM, I would take a similar approach.

Option:
Ask the members of the project if this is still used.

Option:
Otherwise just make it inaccessible (using Access Control) and if no-one complains archive it after some weeks. 8)

Comments
Vishnu Kumar commented Oct 01 '15, 3:23 a.m.

Thanks Ralph.. Last modification query is very helpful as we are using RTC only for project management.

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.