Converting from Oracle 10 -> Oracle 11
CLM 4.0.6
WAS 8.5 Oracle 10 We have installed Oracle 11 on a new machine. We need to migrate from 10 to Oracle 11 before moving to 5.x/6.x. What steps need to happen to migrate to the new DB server? I'm thinking:
|
2 answers
Hi Mahari,
Here is the procedure:
|
Hi Mahari,
Please find the below links and details and also verify it.
1) Preparation :
CLM 4.0.6 supports Oracle 11 from the below system requirements.
https://jazz.net/wiki/bin/view/Deployment/CLMSystemRequirements405406#A6_Databases
2) Backup Source : Find the Backup related CLM.
https://jazz.net/wiki/bin/view/Deployment/BackupCLM
3. CLM Migration considerations.
https://jazz.net/wiki/bin/view/Deployment/MigratingCLMToANewEnvironment
4. Shutdown the server.
5. Edit the database related configuration wrt applications.
eg: edit the teamserver.properties file for all applications in ( JAZZHOME/server/conf ) to point to the new DB.
6. Start the server.
Regards,
Arun.
Comments
Krzysztof Kaźmierczyk
commented Nov 10 '15, 3:23 a.m.
Arun - the question is how to upgrade database, not how to migrate CLM solution to a new environment.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.