Test case estimate hours are converted to days, Is there any way to display as entered?


Rashmi B (19126) | asked Jul 30 '15, 2:30 p.m.
 Hi,
I am providing estimate for my test case execution as 8 hours. this number is automatically converted to 1 day in RQM.
Is there a way to display as it is provided by the user?
I am using RQM 5.0.2

Accepted answer


permanent link
Don Yang (7.7k21108137) | answered Jul 31 '15, 2:48 a.m.
Unfortunately there is no option to display as is without converting, this is consistent behavior in RTC/RQM/RDNG.
Rashmi B selected this answer as the correct answer

One other answer



permanent link
David Babuder (1527) | answered Nov 06 '18, 5:04 p.m.

It should follow a calendar setting. We have automated tests that run for more than 8 hours, and 40 hours of automated testing is 1 day 16 hours, not one week!