Automatic creation of Child task while creating Parent task


Ashok Sonawane (9913) | asked Jun 04 '15, 5:00 a.m.
Hi,

Want to create child task while creating a parent Task.

Consider that, i am creating a WI type Task, while creating   it i need to create its sub task or child task,
will it be possible that i can create a sub task on any trigger or  like that.

Please reply.

One answer



permanent link
Lily Wang (4.9k714) | answered Jun 04 '15, 8:42 p.m.
You can consider to use work item template to create a parent work item and several child work items in one operation.
Otherwise, you have to create a custom advisor and add in a follow-up action of Saving Work Item operation.