Tom Lageson (16263) | asked Jun 22 '09, 9:57 a.m.
The company is taking July 3rd as a holiday. That is in the middle of the sprint. How do I set that day as a holiday for everyone so it is not allocatable on the sprint planning?

- Tom

One answer



permanent link
Michael Scharf (781) | answered Jun 22 '09, 12:08 p.m.
The company is taking July 3rd as a holiday. That is in the middle of
the sprint. How do I set that day as a holiday for everyone so it is
not allocatable on the sprint planning?

Unfortunately, it is currently not possible to add out of office entries
for everyone - each developer has to do it on his own (alternatively, a
user with ADMIN privileges could add the entry manually for everyone)

If you are interested, you can subscribe yourself / comment on the
following related work items:

https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/39772
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/31910

Thanks!

--
MikeS
Jazz Agile Planning team

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.