Hi ,
We are using multiple custom built work items in out project . Some of them are needed to linked in a Parent - Child relationship . Also , we have enabled the operational behavior to ' Resolve a work item only when all children are resolved '
The problem we are facing is that some resources link the ' unresolved' child work items to the parent after the parent is moved to 'Resolved' . But the linking log/timestamp is not recorded in the work item history
Is there a way I can enable logging so that every time work items are linked to each other , the event gets logged in history
Thanks for your answer
Cheers
Achint
|
Accepted answer
History does not contain linking events until 5.0.2
Achint Mathur selected this answer as the correct answer
Comments
Achint Mathur
commented Apr 25 '15, 5:33 p.m.
Thanks Sam . We are on 4.0.6 . I will discuss upgrading with my team . Could you also let me know if there is a way that I can 'lock down' linking after a particular state .
For example :
When a work item is resolved, no more work items can be linked to it ?
Thanks for your time and effort
Achint
sam detweiler
commented Apr 25 '15, 6:36 p.m.
there is nothing in the system that prevents modifying workitems after they are closed.
|
One other answer
This topic in the 5.0.2 help has more information about viewing linking history: Viewing work item history.