query to match Work Hours Done in plan hover


Phil Barrett (33911) | asked Aug 29 '14, 11:55 a.m.

I am trying to create an RTC query that will provide Time Spent or Work Done to match the Progress Report hover in the Plan Detail section of a Plan. The Hover indicates Work hours done: 220 of 220. I cannot get to that number using any of the following columns (or combinations there of):

Corrected Estimate Estimate Maximal Estimate Minimal Estimate Time Spent Consequence Cost

Background: this is a traditional project plan and the work items are on a Closed or Resolved status.

Any help would be greatly appreciated.

One answer



permanent link
Ralph Schoon (62.0k33643) | answered Sep 01 '14, 11:53 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This data is not available as attribute. This is a presentation that is dynamically computed as far as I can tell. You would basically have to query work items and then iterate their hierarchy to collect the data. https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ explains a different approach to calculate data like this.