It's all about the answers!

Ask a question

BIRT Report Security


Matthias Buettgen (23612131) | asked Aug 12 '14, 6:04 p.m.
Hi,

we have created a custom BIRT report which shows some sensative data. Therefore we would like to limit the users who are able to execute this report.

First we thought this could be done by sharing the report template with a specific team, but this doesn't work because even after applying the report template to a specific team it was still visible by all users of the Project Area.

Did we do something wrong or is another intention behind the share report template with "Project Area/Team Area"?

I verified this on RTC 4.0.5 and 4.0.6 and both versions show the same behavior.

Thanks for your help.

Regards
Matthias

One answer



permanent link
Rafik Jaouani (5.0k16) | answered Aug 13 '14, 11:27 a.m.
JAZZ DEVELOPER
edited Aug 13 '14, 11:41 a.m.
4.0.5, 4.0.6, 4.0.7 and 5.0 should all be behaving the same. Adding report resources to team areas and project areas will not affect who can run and who cannot run the reports unless you setup the process roles properly. Look for the Role Operation "Display Report" and make sure it is not assigned to everyone in the team area where the report resource is shared.

Comments
Krzysztof Kaźmierczyk commented Aug 14 '14, 2:46 a.m.

Thanks Rafik for a reply.
Let me ask then one question: What is assigning TA for report resource for?


Rafik Jaouani commented Aug 14 '14, 9:24 a.m.
JAZZ DEVELOPER

I can think of two purposes:
1) Lets you filter the report resources by Team Area in the Eclipse Team Artifacts Navigator
2) Once these reports resources are assigned to Team Areas, you can have finer grained control on their permissions like the scenario described in this forum post.


Krzysztof Kaźmierczyk commented Aug 14 '14, 10:45 a.m.

OK Rafik. I understand it now.
As you are reporting specialist, could you also answer original Matt question?


Rafik Jaouani commented Aug 14 '14, 4:22 p.m. | edited Aug 19 '14, 9:15 a.m.
JAZZ DEVELOPER

I already answered it as follows:
Adding report resources to team areas and project areas will not affect who can run and who cannot run the reports unless you setup the process roles properly. Look for the Role Operation "Display Report" and make sure it is not assigned to everyone in the team area where the report resource is shared.