how to provide permission for changing resource allocation percentage in a project
what is the permission to be given in a role by which one can change the resource allocation percentage in a project.
Please guide ASAP. |
One answer
Hello,
this is currently not possible,
and should be addressed with enhancement Allow role to configure 'Work Allocations' on others profiles (171146)
Eric
Comments
Ayan Paul
commented Aug 07 '14, 8:01 a.m.
I can do it through JAZZ Admin login. Can't it be done through any other id? Hello,
do you mean:
- change my own work allocation
or
- change other user's work allocation
?
Robert Wen
commented Aug 07 '14, 8:11 a.m.
Only users with Administrator privileges can modify other users' records. Looks like this is governed by being in the JazzAdmin group.
Ayan Paul
commented Aug 18 '14, 1:58 a.m.
yes, if the user is project manager and having all rights, even then he is not able to change his team members allocation, only if he is added in JAZZ Administrator, then only it is permissible. Which is not correct.
As a project manager he should have the rights to change the allocation for his team member and he should not have access to JAZZ Admin. Please resolve the same, |
Your answer