Project Member Availablity Demand Reporting


David Beange (111356100) | asked Apr 07 '14, 6:33 a.m.
With CLM V4.0.2 are there any standard reports or queries that could be used to report on the availability and % utilised of team members?

eg
Views such as the below would be useful.
Total Resource demand by week vs capacity
Team Resource demand by week vs capacity
The ability to report on individual projects – time spent vs time allocated / time allocated vs capacity

Or is this something that is only possible Via RRDI or Insight. Would sufficient data be available for extraction and reporting?

Thanks

One answer



permanent link
Rafik Jaouani (5.0k16) | answered Apr 07 '14, 9:37 a.m.
JAZZ DEVELOPER
Hi David,
If you try rendering the Brunup report setting the Detail parameter to high, the report will plot a total team capacity line and a burnup of the team capacity which can be compared against the timespent burnup line.

The capacity data is not available in the data warehouse.