It's all about the answers!

Ask a question

Kanban view for work items not associated with a plan


Javier Plumey (1822) | asked Mar 19 '14, 9:20 a.m.
 We'd like to use RTC for developer and analyst tasks that are not associated with a development effort (no iteration, release, etc.) and we'd prefer to use a Kanban style view for work item in various states.

Is there some way to accomplish this without a plan?

One answer



permanent link
sam detweiler (12.5k6195201) | answered Mar 19 '14, 9:24 a.m.
 no.. you have to have a plan to use the kanban board. 

just make one release and iteration.. no end date. 

Comments
Javier Plumey commented Mar 19 '14, 9:25 a.m.

Seems like a bit of a hack, doesn't it? As a tool for team collaboration, RTC seems focused only on developers.  


sam detweiler commented Mar 19 '14, 10:33 a.m.

has nothing to do with developers.. the implementation of the (task/kanban) Board requires a containing 'plan'.. but to get a Plan you need people(team) and time.  


and I think you are working on SOMETHING with some schedule (time) and there are people doing it (team).. 