RTC Defects -- Single verification changes status of whole work item
![]()
I have a defect in Resolved/Fixed Status with two pending verifications in the Approvals tab (using web client).
When I change the state of one the Verifications to Approved, the Status of the defect automatically changes to Closed. There is still one pending Verification however, so this is not what I want to happen. I would rather the Status did not automatically change at all, but at least it should not change until all verifications are complete. So does anyone know why this happening? Or, if there is a way to prevent this behavior? (Using RTC 4.0.4). Thanks |
Accepted answer
![]()
Dinesh Kumar B (4.1k●4●13)
| answered Mar 07 '14, 3:25 p.m.
JAZZ DEVELOPER edited Mar 07 '14, 3:25 p.m.
also re : When I change the state of one the Verifications to Approved, the Status of the defect automatically changes to Closed
This is configurable from Approval Trackings section : "Define how an approval state change can trigger a workflow action." reachable using : Open PA in Eclipse Client > Process Configuration Tab >Project Configuration > Configuration Data > Work Items > Approval Trackings Pick a Specific Work Flow > Pick a Specific State under an Approval Kind > Mention the Work Flow Action to trigger to. david landis selected this answer as the correct answer
Comments Thanks this is helpful. However it looks like there is no option to trigger the specific workflow transition once all verifications are done. Do you know what I mean? The status should automatically change once all verifications are approved.
|
Comments
approvals do not cause state transitions by default.. so, someone must have configured the project Approval Trackings.