Where is Max Results setting for Change sets in v4.0.3 and newer?


ryosuke oka (17984648) | asked Jan 14 '14, 4:31 a.m.
edited Jan 14 '14, 6:07 a.m. by Krzysztof Kaźmierczyk (7.4k373103)
I found this defect was fixed in v4.0.3 but I could not see Max results setting for Change set in Advanced properties of CCM server.

Dose anyone know the new setting? OR Is there no limit for this?

Defect 231180
Change sets search results does not return all change sets without any warning if the max results setting is larger than 512

Thank you,

One answer



permanent link
Krzysztof Kaźmierczyk (7.4k373103) | answered Jan 14 '14, 6:06 a.m.
Hi Ryosuke,
In Eclipse client click window->preferences and then team->jazz source control->changes. You will have the option Maximum number of changes shown in a change set.

Let us know if it help.

Comments
ryosuke oka commented Jan 14 '14, 7:50 p.m.

Hi Krzysztof,
thank you for your answer.
Yes, you are right about the setting on client.

The issue before v4.0.3 was changing this setting dose not reflect if we set more than 512.
So, I assumed there is server side setting for this but I could not find any setting to set upper limit on the server side.
 

Your answer