We create a Work Breakdown Structure (WBS), which are a set of workitems in a parent child relationship. We set the order of the workitems the order of work. Now when I refresh the plan, the order gets jumbled up. How can I make sure this order is always maintained. This was a known issue in V2.0 but I am seeing the same in V4.0.2.
Someone please let me know the fix for this. Thanks.
|
One answer
![]()
Millard Ellingsworth (2.5k●1●24●31)
| answered Dec 31 '13, 3:28 p.m.
FORUM ADMINISTRATOR / JAZZ DEVELOPER
The Sorting options for the Work Breakdown view are: Estimate, Planned Time, Priority, Ranking and User Defined (at least in the Scrum template). When you say "order of work", to which one are you referring? You might try changing the Sorting to "User Defined" which should remember your ordering. Other than that, on every refresh it should honor the configured sorting option.
|