Problem with planning , hours computation
I created an iteration from 4/15/09 - 5/29/09 , for some reason it seems that a resource that is dedicated 100% to this iteration gets 520 hours. In a previous iteration with similar 6 weeks , Jazz seems to compute 272 hours, which is around what it needs to be (6 weeks * 5 days * 8 hours). Does someone knows about this?
|
One answer
I logged a defect about this -- it ignores the start date of the iteration and counts all hours from today until end of the iteration, regardless of when the iteration starts
Also note that the iteration ends at time 00:00 on the end date so that day is not actually counted as available https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=72755 |