Viewing full workload across multiple teams
![]()
Via the Team Load view I can see the current workload of users for that particular team.
I want to know the progress (have a progress bar) of my users overall, basically an aggregate of all the individual team progress bars averaged into one per user. If a user has 40 hours available in RTC, but 20 go to team A, 20 go to team B, I can only see the progress of either A or B, not the overall usage and planning of his/her full 40 hours. Is there a way to see the overall load of my users, not just the workloads associated with the one team I'm querying? |
2 answers
![]()
arbab.ahmed wrote:
Via the Team Load view I can see the current workload of users for With RTC 2.0 we'll support team load for project areas. I assume this will match what you are looking for. The corresponding work item is https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/68841 -- Cheers, Johannes Agile Planning Team |
|