Is possible have / create a report for step?


Vittorio Napoli (133) | asked Sep 15 '13, 5:18 p.m.
I have a test plan in which there are 220 ​​test cases, each of which has a series of test script with various test step... (normal use of RQM) ...
I need to have a report to show me the totality of the steps and their status (passed, failed, etc ...) ... is there a way to get this report?

Help me please!

One answer



permanent link
Antoinette Iacobo (650712) | answered Sep 16 '13, 11:23 a.m.
 Hi Vittorio,

What reporting solution are you using?  
There isn't any out-of-the-box report for this and I don't believe there is one for RRDI.  This may be possible with Insight.  I'd have to look into it. 