Difference of permission between Project Configuration and Team Configuration


Koji Murofushi (1134) | asked Jul 19 '13, 7:40 a.m.
retagged Jul 22 '13, 4:43 p.m. by Ralph Earle (25739)
There are a lot of differences between permissions under Project Configuration and permissions under Team Configuration.


Why?
Is there any good document to explain why there are such differences?
I'm using RTC 4.0.2.

3 answers



permanent link
Sandy Grewal (1.6k1123) | answered Jul 19 '13, 10:29 a.m.
JAZZ DEVELOPER
Koji,
The difference is because of the levels
Project Configuration - applies to project level
Team Configuration - to the team level

Different things can be done at different levels, hence the different permissions.

IC link has some more details : http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m1/index.jsp?topic=%2Fcom.ibm.jazz.platform.doc%2Ftopics%2Ft_mod_permissions.html

Sandy

Comments
Yoshihisa Komai commented Jul 25 '13, 10:29 a.m.

Hi Sandy,

I've got a related question on this with regards to permissions of work item attachment.
Please give me some advice.

-Under Project Configuration:
Delete attachment
Modify attachment

-Under Team Configuration
Add an attachment
Delete attachment
Modify an attachment
Remove an attachment

Question:
Why only "Delete attachment" and "Modify attachment" exist under "Project Configuration"?
Why "Add an attachment" and "Remove an attachment" don't exist under "Project Configuration"?

I want to know the good example(use case) to utilize those permissions regarding work item attachment.


thanks


Geoffrey Clemm commented Jul 26 '13, 1:36 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

In 4.0.3, there are no attachment permissions in the team configuration list ... only in the project configuration list.


permanent link
Abraham Sweiss (2.4k1231) | answered Jul 19 '13, 11:05 a.m.
The following blog entry should address the why there is a difference.  it gives a bit more detail on the structure of the project area and team area
http://mikemacd.wordpress.com/2010/12/10/rtc-how-big-should-a-project-area-be/

The following article provides some concrete examples on setting up permissions at team scope
https://jazz.net/library/article/215




permanent link
Ken Tessier (84117) | answered Jul 20 '13, 10:49 a.m.
This distinction has been removed in 4.0.3.  Please see Modifying permissions.

Ken

Comments
1
Geoffrey Clemm commented Jul 21 '13, 12:43 a.m. | edited Jul 26 '13, 1:35 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

I would say that in 4.0.3 "the distinction is no longer as obvious".    In particular, the distinction is still made in the Eclipse UI.   Also in the Web UI, the project-level permissions and team-level permissions are combined in a single list for the project area, but if you look at the permissions of a team area, you will only see the team-level permissions and not the project-level permissions.

Your answer