Assign a work item template entry to a specific iteration


Daniel Toczala (88211514) | asked Dec 19 '08, 4:50 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
I am customizing a process, and we have a number of "standard" activities that must be done at different particular iterations of a project. I can create the plan items for these activities by going into the Process Configuration -> Project Area Initialization, and creating the appropriate work item template entries. What I would like to do is to have these assigned to the specific iterations that they belong with. When I create these work items, they all come up with the Planned For field set to unassigned. Is there any way that I can specify default field values in the XML in the Process Configuration Source?

One answer



permanent link
Jared Burns (4.5k29) | answered Jan 07 '09, 12:08 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This isn't possible at this time. If you'd like this feature added,
please file an enhancement request.

Jared Burns
Jazz Process Team


dtoczala wrote:
I am customizing a process, and we have a number of
"standard" activities that must be done at different
particular iterations of a project. I can create the plan items for
these activities by going into the Process Configuration -
Project Area Initialization, and creating the appropriate work item
template entries. What I would like to do is to have these assigned
to the specific iterations that they belong with. When I create these
work items, they all come up with the Planned For field set to
unassigned. Is there any way that I can specify default field values
in the XML in the Process Configuration Source?