Sharing a work item between projects
CLM 4.0.2 - web only
ProjectA
ProjectB
ProjectC
There are 30 work items that need to be tracked in all 3 projects. Is there a way to share the work items, or do they need to be copied and recreated in each project? Each project has different timelines, but once the work is done...it's done for all 3 projects.
What's a best practice for this?
|
One answer
you could use the Cross Project Plan views released in 4.0.1 to track.
course the projects all have to be on the same server where is the work being done? it should be in THAT project. then depends/blocks/... links from the affected workitems in the other projects. |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.