I see the following in my Team Central -> My Open Work Items view. Any thoughts? These are not custom priorities (one is low, the other medium).
|
One answer
I see the following in my Team Central -> My Open Work Items view. This means that you have work items with a priority which is no longer defined in the process configuration. Some reasons why this can happen: - when you delete a priority from the process configuration - when you import work items using the bugzilla importer and the mapping file is incomplete. You can click on the respective bars in Team Central and you will see the affected work items in the work items view. There you can bulk change the priority back to a defined value. -- Regards, Patrick Jazz Work Item Team |