Hi,

I am trying to configure my Jazz Web UI. I was wondering if it is possible to remove / disable a single field / attribute for a certain type of work item? I.e. in a Bug, to disable the "found in" attribute.

TIA.

Regs, Andrew

6 answers



permanent link
Sudhakar Frederick (80113631) | answered Nov 30 '08, 10:48 p.m.
JAZZ DEVELOPER
Cool. Thanks Larry.


websmith wrote:
Yes I meant by changing the editor presentation to not show that
field.

Validation policies and cross-attribute dependencies are enhancements
under consideration, and will when implemented be common between the
Web UI and Eclipse UI.

Larry

permanent link
Lawrence Smith (3764) | answered Nov 21 '08, 3:54 p.m.
JAZZ DEVELOPER
Yes I meant by changing the editor presentation to not show that field.

Validation policies and cross-attribute dependencies are enhancements under consideration, and will when implemented be common between the Web UI and Eclipse UI.

Larry

permanent link
Sudhakar Frederick (80113631) | answered Nov 21 '08, 3:47 p.m.
JAZZ DEVELOPER
Hi Larry,

How do you subtract fields? I can add custom attributes but can't see where to remove fields. Or is it just by changing the Editor presentation?

Also how can I validate data in fields eg. due date must be set to date in the future. Or text entered in Summary must follow a certain pattern?

Cheers
Freddy
The work item types are completely customizable, so you can add or subtract fields by type right now.
...

Larry Smith
IBM RTC Work Item Team

permanent link
Patrick Streule (4.9k21) | answered Nov 21 '08, 8:28 a.m.
JAZZ DEVELOPER
On 2008-11-20 18:07:58 +0100,
andrew.harmel.law@gmail-dot-com.no-spam.invalid (al94781) said:

If I could do this only at certain steps in the Work Item lifecycle,
that would be excellent. I.e. when I log a bug, I can't set the due
date, only the importance. Later on, others can set the due date.

This is a task on our todo list:

https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/64253

Regards,
Patrick
Jazz Work Item Team

permanent link
Lawrence Smith (3764) | answered Nov 20 '08, 4:53 p.m.
JAZZ DEVELOPER
The work item types are completely customizable, so you can add or subtract fields by type right now.

The other proposals were written up by Marcel in Task 64253:
https://jazz.net/jazz/web/projects/Jazz%20Project#action=com.ibm.team.workitem.viewWorkItem&id=64253

... which I found by writing up your request and hitting Find Potential Duplicates :-)

Enjoy.

Larry Smith
IBM RTC Work Item Team

permanent link
Andrew Harmel-Law (14612218) | answered Nov 20 '08, 12:07 p.m.
If I could do this only at certain steps in the Work Item lifecycle, that would be excellent. I.e. when I log a bug, I can't set the due date, only the importance. Later on, others can set the due date.