Change the Resolution field of a Work item


Lucas Gratz (2124) | asked Feb 13 '13, 9:30 a.m.
Hi,

I was wondering if it's possible to change the resolution value of a work item without changing its Status.

I'm using RTC 2.0 and when I set a certain Status that has Resolution values available and save it, the Resolution value turns read only and I can't edit it anymore.

But what if the Resolution was wrongly assigned and I want to change it without changing the Status? Is it possible? Are there any workarounds?

Thanks

One answer



permanent link
Lucas Gratz (2124) | answered Feb 13 '13, 10:01 a.m.
Found a topic about it, pretty much the same issue I have.
Apparently there is no solution, I'll try to use a custom field instead of the default Resolution.

https://jazz.net/forum/questions/100972/updating-resolution-without-changing-state

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.